In December 2012, Shire Computer’s management establishes the year 2013 predetermined overhead rate based on direct labor cost.

In December 2012, Shire Computer’s management establishes the year 2013 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $826,800 of overhead costs and $520,000 of direct labor cost in year 2013. During March 2013, Shire began and completed Job No. 13-56.

1. What is the predetermined overhead rate for year 2013?

save image
2.
Use the information on the following job cost sheet. (Round your answer to the nearest dollar amount.)


JOB COST SHEET
  Customer’s Name   Keiser Co. Job No. 13-56  
 
 
 
  Job Description   5 plasma monitors—61 inch    
 

 
  Direct Materials   Direct Labor   Overhead
Costs Applied
 
 
 
 
 
  Date Requisition No. Amount   Time-Ticket No. Amount   Rate Amount  
  Mar. 8 4-129 $ 4,000     T-306 $ 620          
  Mar. 11 4-142   6,900     T-432   1,290          
  Mar. 18 4-167   3,500     T-456   1,280          
   

   

   
 
  Totals                      
   



   



   

 



 
Determine the total cost of the job.

Total cost of the job $22,662