QS 24-16 Manufacturing cycle time and efficiency LO A4 The following information is from a manufacturing company. Process time 15 minutes Inspection time 2 minutes Move time 6.4 minutes Wait time 36.6 minutes a. Compute manufacturing cycle time

QS 24-16 Manufacturing cycle time and efficiency LO A4
The following information is from a manufacturing company.
   
   
  Process time 15 minutes  
  Inspection time 2 minutes  
  Move time 6.4 minutes  
  Wait time 36.6 minutes  


a. Compute manufacturing cycle time